Calculations for Footing Plain Cement Concrete
The dimensions of the PCC bed depend upon the size of the footing. As we have the given length of footing = 1.2m & width = 1.4m. The length and width of PCC will be determined by adding 100mm at either end of each dimension
Calculations for Footing PCC
Length of PCC = Length of footing + 0.1m + 0.1m &
Width of PCC = Width of footing + 0.1m + 0.1m
Length of PCC = 1.2 + 0.1 + 0.1 = 1.4m
Width of PCC = 1.4 + 0.1 + 0.1 = 1.6m
The thickness of PCC will also be taken as 100mm i.e, 0.1m
Quantity of concrete:
Volume of concrete = Length x width x Depth = 1.4 x 1.6 x 0.1 = 0.224m³
It should be noted that this volume is the wet volume of the concrete. So we need to convert this wet volume to dry volume by multiplying the wet
volume by a constant of 1.54.
Dry volume = wet volume x 1.54
Dry volume = 0.224 x 1.54 = 0.344m³
The volume of Cement:
Volume of Cement = (ratio of Cement/total ratio) x (Dry volume)
Volume of Cement = (1/7) x (0.344) = 0.049m³
Number of Cement bags required = volume of Cement/volume of 1 bag of cement
[volume of 1bag = 0.035m³]Number of Cement bags = 0.049/0.035 = 1.4 bags
The volume of sand:
Volume of sand = (ratio of sand/total ratio) x (dry volume)
= (2/7) (0.344) = 0.098m³
The volume of aggregate:
Volume of aggregate = (ratio of aggregate/total ratio) x (dry volume) = (4/7) (0.344) = 0.19m³
Shuttering Area
Shuttering Area = Peripheral Area of PCC = Area of 4 sides
= (Length x Depth) + (Width x Depth) + (Length x Depth) + (Width x Depth)
= 2(Length x Depth) + 2(Width x Depth) = 2Depth (Length + Width) = 2 x 0.1(1.4 + 1.6) = 0.6 m2
Bitumen paint Area
Bitumen paint Area = Peripheral area of PCC + (Top area of PCC – Top/bottom area of footing)
= 0.6 + {(1.4 x 1.6) – (1.2 x 1.4)} = 1.16 m2
Polythene sheet
Polythene sheet = Length x width m2
= 1.4 x 1.6 = 2.24 m2
Termite Control
Termite area = Length x width m2
= 1.4 x 1.6 = 2.24 m2