Nominate an experienced Site Engineer at site.

Planning

Obtain Dia wise and grade wise quantities from designer for lump sum contract if drawings were not available at initial stages of project for planning procurement.

INFRASTRUCTURE

See More Minimum Reinforcement in Slabs and Beams

Procurement

Indent for quarterly requirement 30 days in advance apart from total requirement in phase.

Collection of Civil Engineering Ebooks Click Here

Receipt at site

MAKE SURE ALL THE MATERIAL SHALL BE RECEIVED IN DAY LIGHT ONLY.

Keep an escort from weigh bridge to site yard after weighing and for weighing of tare weight of vehicle .

Controlling Reinforcement Activities in Construction Site to be followed.