Detailed estimating, sometimes referred to as “Prime Cost”, “Bottoms Up” or “Grass Roots” estimating requires a thorough and detailed analysis of all the tasks required to deliver a project or product. A “good” estimate maximizes the return on this investment by obtaining the highest value at the lowest cost.The estimate can be developed using a combination of estimating methods.An estimate is a calculation of the quantities of various items of work, and the expenses likely to be incurred there on. The total of these probable expenses to be incurred on the work is known as estimated cost of the work.Estimate for Residential Building

Description of Work

Earth work excavation

Sand filling for foundation/basement

P.C.C 1:5:10 mix for foundation , 40mm metal

R.C.C  1:2:4 for Beam, sunshade, loft,  roof, using tor steel rods

DUMMY CONCRETE 1:3:6

Centering & Scaffolding Work using tor steel rods & mild steel

Reinforcement Work

Brick work in c.m. 1:5  in foundation with chamber bricks

Brick work in c.m. 1:5 with chamber bricks for superstructure

Plastering for all walls C.M 1:5 mix, 12mm thick  thorouly inner &  outer

Plastering for ceiling in C.M 1:3 mix 10mm thick

Tiles flooring

Calculate House Estimate

Weathering course concrete

Weathering course tiles

White wash for Inner & Outer

colour wash for Inner & Outer

Doors & Windows

Electrical work

Plumbing  work

Septic tank work

How to Estimate House Construction Cost?

Bore work arrangements

Cupboard work arrangements

Grill works

Elevation item of work

Miscellaneous items of work

In case the funds avilable are less than the estimated cost the work is done in part or by reducing it or specifications are altered, the following require-ment are necessary for preparing an estimate.
a ) Drawings like plan, elevation and sections of important points.
b) Detailed specifications about workmenship & properties of materials etc.
c) Standard schedule of rates of the current year.

Note: cost of materials and labor charges varied just for sample, reference

Free Download wait for Count Download 

Detailed Estimate Excel Sheet Free Download Clicks Here Below wait for count down.

Exit mobile version