How to Calculate Quantity of Materials for PCC Slab
The quantity of materials required for a plain cement concrete (PCC) slab can be calculated by considering the volume of concrete required and then converting it into the required amount of cement, sand, aggregate, and water.
Here is the formula for calculating the volume of concrete required for a slab:
Volume of concrete = Length x Breadth x Thickness
Next, you can calculate the amount of cement, sand, aggregate, and water required for the concrete mix, based on the mix design proportions.
Calculate Quantity of Materials for PCC Slab For Example:
let’s consider an example of a PCC slab with the following specifications:
Length = 10 meters
Breadth = 5 meters
Thickness = 0.15 meters
Volume of concrete = Length x Breadth x Thickness
= 10 x 5 x 0.15
= 7.5 cubic meters
Assume a mix design of 1:2:4 (cement:sand:aggregate) with a water-cement ratio of 0.5.
Amount of cement required = Volume of concrete x (cement content / (cement + sand + aggregate))
= 7.5 x (1 / (1 + 2 + 4))
= 7.5 x (1 / 7)
= 1.07 cubic meters
Amount of sand required = Volume of concrete x (sand content / (cement + sand + aggregate))
= 7.5 x (2 / (1 + 2 + 4))
= 7.5 x (2 / 7)
= 2.14 cubic meters
Amount of aggregate required = Volume of concrete x (aggregate content / (cement + sand + aggregate))
= 7.5 x (4 / (1 + 2 + 4))
= 7.5 x (4 / 7)
= 4.29 cubic meters
Amount of water required = Volume of concrete x water-cement ratio
= 7.5 x 0.5
= 3.75 cubic meters
Join Telegram Channel Click Here
So, for the given example, you will need 1.07 cubic meters of cement, 2.14 cubic meters of sand, 4.29 cubic meters of aggregate, and 3.75 cubic meters of water to make 7.5 cubic meters of PCC.
Note: The mix design proportions can vary based on the type of structure and the local building codes. Hence, it is advisable to consult with a structural engineer to determine the correct mix design proportions for your project.