Consumptions for Plastering, Brickworks, Concreting

Consumption of different materials of construction in the corresponding contract items of works shall  be computed on the basis of the quantities shown in below, subject to a variation of plus / minus  five percent. Where, however, the circumstances of work so require, the Engineer-in-charge shall be  competent to allow (for record reason) for a greater variation.

Note. :-  This statement is based on the following assumptions:

(1)         That dry sand with necessary allowance for bulking is used.

(2)         That the size of bricks shall be 9 ¾˝ x 4 ¾˝ x 2 ¾˝.

(3)         Volume of 1 bag (50 Kg) cement = 0.035 m3

QUANTITIES OF MATERIALS REQUIRED FOR PLASTERING, BRICKWORK,CONCRETING & OTHER ITEMS

Sl.

No.

Description of items Unit Quantities of materials required.
1. 10 mm cement plaster  (4 : 1) 100 m² Sand 1.200 m3

Cement 428.6 kg

2. 15 mm cement plaster  (4 : 1) 100 m² Sand 1.460 m3

Cement 657.1 kg

3. 20 mm cement plaster  (4 : 1) 100 m² Sand 2.170 m3

Cement  778.6 kg

4. 15 mm cement plaster  (6 : 1) 100 m² Sand 1.800 m3

Cement 428.6 kg

5. 20 mm cement plaster  (6 : 1) 100 m² Sand 2.400 m3

Cement 571.4 kg

6. Ruled pointing m3 Sand 0.370 m3

Cement 174.3 kg

7. Brickwork in cement mortar  (1 : 3) m3 Brick 388 nos.

Cement 152.9 kg

Sand 0.320 m3

8. Brickwork in cement mortar  (1 : 4) m3 Brick 388 nos.

Cement 118.6 kg

Sand 0.330 m3

9. Brickwork in cement mortar  (1 : 6) m3 Brick 388 nos.

Cement 78.57 kg

Sand 0.330 m3

10. Random / Coursed / Rubble masonry in cement

mortar in road & jhora works (1 : 4)

m3 Stone 1.250 m3

Cement 128.6 kg

Sand 0.360 m3

11. Random / Coursed / Rubble masonry in cement

mortar in road & jhora works (1 : 5)

m3 Stone 1.250 m3

Cement 101.4 kg

Sand 0.374 m3

12. Random / Coursed / Rubble masonry in cement mortar in road & jhora works (1 : 6) m3 Stone 1.250 m3

Cement 92.9 kg

Sand 0.385 m3

13. Square & coursed Rubble masonry in cement mortar in road & jhora works (1 : 4) m3 Stone 1.250 m3

Cement 107.1 kg

Sand 0.300 m3

14. Square & coursed Rubble masonry in cement mortar in road & jhora works (1 : 5) m3 Stone 1.250 m3

Cement 89.1 kg

Sand 0.312 m3

15. Square & coursed Rubble masonry in cement mortar in road & jhora works (1 : 6) m3 Stone 1.250 m3

Cement 76.4 kg

Sand 0.321 m3

16. Nominal mix cement concrete  (1 : 1 1 / 2  : 3) m3 Stone chips (6 to 20 mm) 0.860 m3

Cement 408.6 kg

Sand 0.430 m3

17. Nominal mix cement concrete  (1 : 2 : 4) m3 Stone chips (6 to 20 mm) 0.880 m3

Cement 314.3 kg

Sand 0.440 m3

18. Nominal mix cement concrete  (1 : 3 : 6) m3 Stone chips (6 to 20 mm) 0.940 m3

Cement 222.9 kg

Sand 0.470 m3

19. Nominal mix cement concrete  (1 : 4 : 8) m3 Stone chips (6 to 20 mm) 0.960 m3

Cement 171.4 kg

Sand 0.480 m3

20. Neat cement punning 100 m 2 cement  217.1 kg
21. Single brick flat soling 100 m 2 Brick  3228 nos.
22. Brick on edge flooring 100 m 2 Brick  5380 nos.
23. 75 mm wide brick on end edging 100 m 2 Brick  800 nos.
24. 75 mm wide brick on edge edging 100 m 2 Brick  400 nos.
25. Boulder for pitching apron & sausage work m3 Boulder  0.90 m3

 

 

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button
Follow Engineers

Civil Engineering Job Update in WhatsApp

click on the below link to join
Join Now
close-link
Join over 1000+ Civil Engineers!

Civil Engineering Job Updates in WhatsApp

Daily Civil Jobs Updates click on the below link.
JOIN NOW!
close-link
World’s Biggest Cruise Ship Construction Work Checklist Autocad 2d Plan with 3d Elevation