Quantities of Materials Required for Plastering, Brickwork,Concreting
Quantities of Materials Required for Plastering, Brickwork,Concreting
Consumptions for Plastering, Brickworks, Concreting
Consumption of different materials of construction in the corresponding contract items of works shall ย be computed on the basis of the quantities shown in below, subject to a variation of plus / minus ย five percent. Where, however, the circumstances of work so require, the Engineer-in-charge shall be ย competent to allow (for record reason) for a greater variation.
Note. :-ย This statement is based on the following assumptions:
(1)ย ย ย ย ย ย ย ย That dry sand with necessary allowance for bulking is used.
(2)ย ย ย ย ย ย ย ย That the size of bricks shall be 9 ยพห x 4 ยพห x 2 ยพห.
(3)ย ย ย ย ย ย ย ย Volume of 1 bag (50 Kg) cement = 0.035 m3
QUANTITIES OF MATERIALS REQUIRED FOR PLASTERING, BRICKWORK,CONCRETING & OTHER ITEMS
Sl.
No. |
Description of items | Unit | Quantities of materials required. |
1. | 10 mm cement plasterย (4 : 1) | 100 mยฒ | Sand 1.200 m3
Cement 428.6 kg |
2. | 15 mm cement plasterย (4 : 1) | 100 mยฒ | Sand 1.460 m3
Cement 657.1 kg |
3. | 20 mm cement plasterย (4 : 1) | 100 mยฒ | Sand 2.170 m3
Cement ย 778.6 kg |
4. | 15 mm cement plasterย (6 : 1) | 100 mยฒ | Sand 1.800 m3
Cement 428.6 kg |
5. | 20 mm cement plasterย (6 : 1) | 100 mยฒ | Sand 2.400 m3
Cement 571.4 kg |
6. | Ruled pointing | m3 | Sand 0.370 m3
Cement 174.3 kg |
7. | Brickwork in cement mortarย (1 : 3) | m3 | Brick 388 nos.
Cement 152.9 kg Sand 0.320 m3 |
8. | Brickwork in cement mortarย (1 : 4) | m3 | Brick 388 nos.
Cement 118.6 kg Sand 0.330 m3 |
9. | Brickwork in cement mortarย (1 : 6) | m3 | Brick 388 nos.
Cement 78.57 kg Sand 0.330 m3 |
10. | Random / Coursed / Rubble masonry in cement
mortar in road & jhora works (1 : 4) |
m3 | Stone 1.250 m3
Cement 128.6 kg Sand 0.360 m3 |
11. | Random / Coursed / Rubble masonry in cement
mortar in road & jhora works (1 : 5) |
m3 | Stone 1.250 m3
Cement 101.4 kg Sand 0.374 m3 |
12. | Random / Coursed / Rubble masonry in cement mortar in road & jhora works (1 : 6) | m3 | Stone 1.250 m3
Cement 92.9 kg Sand 0.385 m3 |
13. | Square & coursed Rubble masonry in cement mortar in road & jhora works (1 : 4) | m3 | Stone 1.250 m3
Cement 107.1 kg Sand 0.300 m3 |
14. | Square & coursed Rubble masonry in cement mortar in road & jhora works (1 : 5) | m3 | Stone 1.250 m3
Cement 89.1 kg Sand 0.312 m3 |
15. | Square & coursed Rubble masonry in cement mortar in road & jhora works (1 : 6) | m3 | Stone 1.250 m3
Cement 76.4 kg Sand 0.321 m3 |
16. | Nominal mix cement concreteย (1 : 1 1 / 2ย : 3) | m3 | Stone chips (6 to 20 mm) 0.860 m3
Cement 408.6 kg Sand 0.430 m3 |
17. | Nominal mix cement concreteย (1 : 2 : 4) | m3 | Stone chips (6 to 20 mm) 0.880 m3
Cement 314.3 kg Sand 0.440 m3 |
18. | Nominal mix cement concreteย (1 : 3 : 6) | m3 | Stone chips (6 to 20 mm) 0.940 m3
Cement 222.9 kg Sand 0.470 m3 |
19. | Nominal mix cement concreteย (1 : 4 : 8) | m3 | Stone chips (6 to 20 mm) 0.960 m3
Cement 171.4 kg Sand 0.480 m3 |
20. | Neat cement punning | 100 m 2 | cementย 217.1 kg |
21. | Single brick flat soling | 100 m 2 | Brickย 3228 nos. |
22. | Brick on edge flooring | 100 m 2 | Brickย 5380 nos. |
23. | 75 mm wide brick on end edging | 100 m 2 | Brickย 800 nos. |
24. | 75 mm wide brick on edge edging | 100 m 2 | Brickย 400 nos. |
25. | Boulder for pitching apron & sausage work | m3 | Boulderย 0.90 m3 |