Methodology of Post-Tensioning work

Methodology of Post-tensioning work

Post-tensioningย  workย  isย  dividedย  intoย  threeย  majorย  activities.ย  Theย  general methodology is given below.

  1. Profiling.
  2. Stressing.
  3. Grouting.

1) Profiling:

  • Read theย  drawingsย  andย  identifyย  typeย  ofย  tendons,ย  layout,ย  locations,ย  andย  number of strands per tendon, sequence of laying, number of tendons per pour, etc.
  • Calculate the materials requirement such as Tube Units, Bearing Plates, Wedges, Sheathing and Prestressing Steel (HTS).
  • Calculate the cut length of Strand inclusive of Jack Grip length & profile for each tendon and prepare Strand cutting schedule as per drawing.
  • HT Strand must be cut by using cut-off wheel/abrasion blade.H T Strand shall be uncoiled using coil dispenser and it should not contact soil or dust while cutting.
  • Mark the Tendons as per Tendon layout drawing, after the completion of formwork& reinforcement.Fixย  theย  fabricatedย  tendonย  supportย  barsย  (barย  chairs)ย  rigidlyย  atย  everyย  1mย  (max.) interval according to the tendon layout and profile drawings.
  • Lay the sheathing over the tendon support bars as per the tendon layout drawing and jointhe ducts using couplers and seal the joint using self-adhesive tape.
  • Thread therequired number of Strands into Sheathing according to the ย Tendon type (strand schedule) and tie thesheathing with Bar Chairs using Binding wires rigidly.
  • Profiling of Tendons, both horizontally and vertically as per drawingsand arresting it rigidly to avoid any disturbances in profile during concreting.
  • Fix the Stressing anchorages and make Dead-end anchorages position as per the layout drawing. Fix the Grout vents at end portions and Air vents at high profile locations and seal it properly.
  • Tie Bursting and Spiral reinforcements at the anchorages zones as per the details given in drawing. Final checking of all Tendons for profiling, supporting and sealing after the completion of reinforcement and formwork works and before concreting.

2) Stressing:

  • Stressing shallย  beย  carriedย  outย  onlyย  afterย  theย  concreteย  hasย  attainedtheย  required Compressive Strength and age of concrete as specified in the drawing.
  • Check theย  Stressingย  equipmentsย  andย  hosesย  beforeย  stressingย  toย  ensureย  proper/smooth functioning.
  • H T Strand/Wire/Bars shall be completely cleaned (oil, dust & etc.) for gripping of Jacks. Stressing can be carried out stage by stage if required, as per drawing.
  • Calculate the Elongation or Modified Elongation for each tendon as per the physical values in TC.
  • Calculate the Jack Pressure for the Design Load including Jack & Anchorage losses.
  • Stressing shall be carried out only as per the specified sequence. Load shall be applied to the tendons by using calibrated hydraulic pumps and jacks and monitored through calibrated Pressure gauges.
  • Fix the Bearing plate to the tube unit and lock it by wedges and mark aย  referenceย  pointย  onย  Strandย  toย  measure
  • Stressing canย  be performed in single / multi strokes depend on Jack piston length.Fix the Hydraulic Jack (Mono/Multi) at stressing end (Single/Double) andย  ensure proper seating of jack with bearing plate and also connect the Jack & Pump by hydraulic hosepipes.
  • Apply theย  calculatedย  pressureย  (load)ย  graduallyย  inย  incrementalย  basisย  onย  eachย  strandย  orย  tendonย  byย  usingย  hydraulicย  Jackย  and
  • Apply jack pressure at both ends simultaneously for double-end stressing.While applying load check for required elongation & jack pressure duringย  stressing and also note the Jack pressure & Elongation reading at every interval / stage in stressing format.Compute the total Jack Pressure applied and the total elongation arrivedย  during stressing.
  • If elongationย  reached,ย  butย  pressureย  notย  reachedย  applyย  5%ย  additionalย ย ย  ย  Ifย  pressureย  reached,ย  butย  elongationย  notย  reachedย  applyย  5% additional pressure. After applying the additional pressure / elongation, if the Stressing resultย ย ย  is within +/-5%, release the jack pressure slowly and then proceed for next stressing. Ifย  theย  stressingย  resultย  /ย  valueย  isย  moreย  thanย  +/-5%ย  informย  theย  Designย ย ย  Engineerย  forย  furtherย  instruction.ย  Sameย  methodย  shallย  beย  followed ย forย  all other Strands / Tendons.12 hours after the completion of stressing of all tendons, cut the strandsย  leaving 25mm from the face of wedges by using angle grinder.
  • After cuttingย  fillย  theย  recessย  pocketsย  (Stressingย  pocket)ย  inย  layersย  usingย ย ย  approved materials.

3) Grouting:

  • After theย  settingย  /ย  curingย  timeย  ofย  recessย  pockets,ย  flushย  theย  tendonsย ย ย  (sheathing) completely by water and then by compressed air. Potable water and OPC Cement should be used for preparation of grout. Suitableย  admixtureย  (Non-Aluminiumย  /ย  Non-Chlorideย  based)ย  mayย  be added to the grout as per specification.Fix the valves at all grout and air vents and also fix the pressure gauge.Mix Water followed by Cement of ratio 0.40 in the grouting machine.The grout shall be mixed in mixture for 2-3 minutes and until pumping of
  • Grout should be colloidal mixture and free from any lumps and it should passed through sieve.Pump the grout into the tendon through grout vent pipe (inlet) and releaseย  the air inside the tendon through air vents.Plug all air vent pipes and also the outlet vent pipe after consistent groutย ย ย  is passed.
  • After pluggingย  allย  theย  ventsย  pipesย  tightly,ย  builtย  theย  pressureย  ofย  5kg/cm2 and maintain for one minute. Then close the inlet valve also. The same method shall be followed for all other tendons.
  • Grouting should be performed continuously to avoid grout setting. Any breakageย  occurredย  duringย  grouting,ย  flushย  theย  tendonย  withย  waterย  and compressed air and do fresh grouting.
  • Clean the vicinity by water after the grouting is completed.
  • Cut all vent pipes projecting outside the surface after the grout is set.

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button
Follow Engineers

Civil Engineering Job Update in WhatsApp

click on the below link to join
Join Now
close-link
Join over 1000+ Civil Engineers!

Civil Engineering Job Updates in WhatsApp

Daily Civil Jobs Updates click on the below link.
JOIN NOW!
close-link
Worldโ€™s Biggest Cruise Ship Construction Work Checklist Autocad 2d Plan with 3d Elevation