A site engineer offers advice in the planning, co-ordination and supervision of technical aspects of construction projects. A site engineer’s role is vital to a construction project: they have a number of responsibilities including solving technical issues, providing advice, management and preparing reports.
Minimum thickness of slab is 125 mm.
Water absorption should not be more than 15 %.
Dimension tolerance for cubes + – 2 mm.
Compressive strength of Bricks is 3.5 N /mm2
Maximum Free fall of concrete allowed is 1.50 m.
In soil filling as per IS code for every 100 sqm 3 sample for core cutting test should be taken.
Electrical conduits shall not run in column
Earth work excavation for basement above 3 m should be stepped form
Any back filling shall be compacted 95% of dry density at the optimum moisture content and in layers not more than 200mm for filling above structure and 300 mm for no structure
F soling is specified the soling stones shall be laid at 45° to 60° inclination (and not vertical) with interstices filled with sand or moorum.
A set of cube tests shall be carried out for each 30 cum of concrete / each levels of casting / each batch
of cement.
Water cement ratio for different grades of concrete shall not exceed 0.45 for M20 and above and 0.50 For M10 / M15 contractor
For concrete grades M20 and above approved admixture shall be used as per mix design requirements.
Cement shall be stored in dry places on a raised platform about 200mm above floor level and 300mm away from walls. Bags to be stacked not more than 10 bags high in such a manner that it is adequately protected from moisture and contamination.
Samples from fresh concrete shall be taken and at least a set of 6 cubes of 150mm shall be prepared and
cured. 3 Cubes each at 7 days and 28 days shall be tested for compressive strength. The test results
should be submitted to engineer for approval. If results are unsatisfactory necessary action/rectification/remedial measures has to be exercised.
Water used for both mixing and curing shall be clean and free from injurious amounts of oils, acids, alkalies, salts, sugar and organic materials or other substances that may be deleterious to concrete or steel. The ph shall be generally between 6 and 8.
Read More Work activities for Site Engineer
Cement shall be tested for its setting.
1. The initial setting time shall not be less than 30 minutes.
2. The final setting time shall not be more than 10 hours.
Slump IS 456
Lightly reinforced 25 – 75 mm
Heavily reinforced 75 – 100 mm
Trench fill (insitu & Tremie) 100 – 150 mm (For Tremie no need of vibrator)
Curing Days Required
Super Sulphate cement : 7 days
Ordinary Portland cement OPC : 10 days
Minerals and Admixture added cement : 14 days
Cube Samples
1 – 5 M3 : 1 No.
6 – 15 M3 : 2 No’s
16 – 30 M3 : 3 No’s
31 – 50 M3 : 4 No’s
Above 50 M3 : 4 + 1 No of addition sample for each 50 M3.