Thumb rule requirement of standard materials in high raised building

Thumb rule requirement of standard materials and standard calculation in high raised building

Steel =3 to 5 kg / sft

Cement =.5bags/ sft

RMC =.05 m3/sft

Block =12.5 nos /sqm

Electrical cast = Rs 133/sft

Plumbing cost = Rs 126/sft

Fire fighting cost = Rs 40/sft

External development = Rs 94.5/sft

Civil works-Structure = RS 751.25/sft

Finishing works = RS 467.50/sft

200 mm in cm 1:6 .124Bags /sqm

200 mm in cm 1:4 0.206 bags/sqm

150 mm in cm 1:6 0.093 bags/sqm

150mm in cm 1:4 0.144 bags/sqm

100 mm in cm 1:4 0.103 bags/sqm

Ceiling plastering 0.11 bags/sqm

Wall plastering 0.09 bags/sqm

Rough plastering 0.09 bags/sqm

Duct plastering 0.09 bags/sqm

External plastering 0.175 bags/sqm

lathen plastering 0.55 bags/sqm

stucco plaster 0.175 bags/sqm

100 mm plaster band 0.012 bags/rmt

pcc 1: 4: 8 3.4 bags/cum

pcc 1:5:10 2.52 bags/cum

pcc 1:3:6 4.2 bags/cum

pcc 1:2:4 6.02 bags/cum

230 mm brick 0.876 bags/cum

115 mm brick work 0.218 bags/cum

vdf 100 mm thick 0.82 bags/sqm

granolithic flooring 40 mm 0.35 bags/sqm

granolithic flooring 20 mm 0.28 bags/sqm

anti-skid 0.28 bags/sqm

ceramic 0.28 bags/sqm

vertified tile flooring 0.28 bags/sqm

vertified tile dado 0.27 bags/sqm

cerami dado 0.27 bags/sqm

marble flooring 0.3 bags/sqm

100 mm heigh marble skerting 0.027 bags/rmt

marble glading 0.27 bags/sqm

terracota tle flooring 0.3 bags/sqm

mangalore tile 0.3 bags/sqm

Door frame fixing 0.17 bags/sqm

water proofing for sunken slab 0.23 bags/sqm

water proofing for walls 0.23 bags/sqm

water proofing for balcony/toilets 0.65 bags/sqm

Ant terminate treatment chemical Name is chloropyrifoc 20% . Diluting

5 Lit of Chemical with 95 Lit of water and usage is 7.5 Sqm Per liter {Diluted} .To Provide 1” Dia hole And Deep1Foot.

 

Labour Productivity:

Brick work 1 mason

1 Men mazdoor 1.25 cm

1 Women Mazdoor

Wall Plastering 1 mason

1 Men mazdoor 10 sqm

1 Women Mazdoor

Ceiling Plastering 1 mason

1 Men mazdoor 8 sqm

1 Women Mazdoor

External Plastering 1 mason

1 Men mazdoor 8 sqm

1 Women Mazdoor

Blockk work 8” 1 mason

1 Men mazdoor 10 sqm

1 Women Mazdoor

Blockk work 6” 1 mason

1 Men mazdoor 8 sqm

1 Women Mazdoor

Blockk work 4” 1 mason

1 Men mazdoor 8 sqm

1 Women Mazdoor

Carpenter 1 Skilled

1 Un skilled 4 Sqm

Bar bender 1 Skilled

1 UN skilled 200Kg

Tile work 1 Mason

1M Mazdoor 10 Sqm

Painter skilled OBD 600 Sft

Emulsion 800 Sft

Putty 600 Sft

Primer 800 Sft

One Sqm=10.763Sft

One Cum=35.314 Cft

One Acres=4046.873 Sqm=43560.17 Sft=4840.019Yards

One Cubic meter = 1000 litere

One Meter=3.280Feet

One Mile =1609.344 meter

One Acre = 100 cent

One ground =2400 Sft=5.51 cent

½ ground =2.75 cent

One Mile =8 Furlong

One cement bag=1.25 Cft

One Forma box =1*1*1.25 feet

External Painting

Ace-Low quality

Apex-Medium Quality

Apex ultima –High Quality

 

Exit mobile version