Thumb rule requirement of standard materials in high raised building

Thumb rule requirement of standard materials in high raised building

Thumb rule requirement of standard materials and standard calculation in high raised building

Steel =3 to 5 kg / sft

Cement =.5bags/ sft

RMC =.05 m3/sft

Block =12.5 nos /sqm

Electrical cast = Rs 133/sft

Plumbing cost = Rs 126/sft

Fire fighting cost = Rs 40/sft

External development = Rs 94.5/sft

Civil works-Structure = RS 751.25/sft

Finishing works = RS 467.50/sft

200 mm in cm 1:6 .124Bags /sqm

200 mm in cm 1:4 0.206 bags/sqm

150 mm in cm 1:6 0.093 bags/sqm

150mm in cm 1:4 0.144 bags/sqm

100 mm in cm 1:4 0.103 bags/sqm

Ceiling plastering 0.11 bags/sqm

Wall plastering 0.09 bags/sqm

Rough plastering 0.09 bags/sqm

Duct plastering 0.09 bags/sqm

External plastering 0.175 bags/sqm

lathen plastering 0.55 bags/sqm

stucco plaster 0.175 bags/sqm

100 mm plaster band 0.012 bags/rmt

pcc 1: 4: 8 3.4 bags/cum

pcc 1:5:10 2.52 bags/cum

pcc 1:3:6 4.2 bags/cum

pcc 1:2:4 6.02 bags/cum

230 mm brick 0.876 bags/cum

115 mm brick work 0.218 bags/cum

vdf 100 mm thick 0.82 bags/sqm

granolithic flooring 40 mm 0.35 bags/sqm

granolithic flooring 20 mm 0.28 bags/sqm

anti-skid 0.28 bags/sqm

ceramic 0.28 bags/sqm

vertified tile flooring 0.28 bags/sqm

vertified tile dado 0.27 bags/sqm

cerami dado 0.27 bags/sqm

marble flooring 0.3 bags/sqm

100 mm heigh marble skerting 0.027 bags/rmt

marble glading 0.27 bags/sqm

terracota tle flooring 0.3 bags/sqm

mangalore tile 0.3 bags/sqm

Door frame fixing 0.17 bags/sqm

water proofing for sunken slab 0.23 bags/sqm

water proofing for walls 0.23 bags/sqm

water proofing for balcony/toilets 0.65 bags/sqm

Ant terminate treatment chemical Name is chloropyrifoc 20% . Diluting

5 Lit of Chemical with 95 Lit of water and usage is 7.5 Sqm Per liter {Diluted} .To Provide 1” Dia hole And Deep1Foot.

 

Labour Productivity:

Brick work 1 mason

1 Men mazdoor 1.25 cm

1 Women Mazdoor

Wall Plastering 1 mason

1 Men mazdoor 10 sqm

1 Women Mazdoor

Ceiling Plastering 1 mason

1 Men mazdoor 8 sqm

1 Women Mazdoor

External Plastering 1 mason

1 Men mazdoor 8 sqm

1 Women Mazdoor

Blockk work 8” 1 mason

1 Men mazdoor 10 sqm

1 Women Mazdoor

Blockk work 6” 1 mason

1 Men mazdoor 8 sqm

1 Women Mazdoor

Blockk work 4” 1 mason

1 Men mazdoor 8 sqm

1 Women Mazdoor

Carpenter 1 Skilled

1 Un skilled 4 Sqm

Bar bender 1 Skilled

1 UN skilled 200Kg

Tile work 1 Mason

1M Mazdoor 10 Sqm

Painter skilled OBD 600 Sft

Emulsion 800 Sft

Putty 600 Sft

Primer 800 Sft

One Sqm=10.763Sft

One Cum=35.314 Cft

One Acres=4046.873 Sqm=43560.17 Sft=4840.019Yards

One Cubic meter = 1000 litere

One Meter=3.280Feet

One Mile =1609.344 meter

One Acre = 100 cent

One ground =2400 Sft=5.51 cent

½ ground =2.75 cent

One Mile =8 Furlong

One cement bag=1.25 Cft

One Forma box =1*1*1.25 feet

External Painting

Ace-Low quality

Apex-Medium Quality

Apex ultima –High Quality

 